Eromanga Basin, South Australia
Eromanga HMS Project
- 4,000m HMS air-core drilling program to commence in mid-September
- Drill permits received on time from the SA Department for Energy and Mining (DEM)
- Heritage clearance survey completed on time by Arabana traditional owners
– all planned targets approved EL7071, EL7072 and EL6195 - Drilling to be undertaken on the Nilpinna and Douglas Creek Tenements, see map below
- Drill contractor secured – McLeod Drilling
- Altitude’s expert Heavy Mineral Sands (HMS) Consultant, Ian Warland to oversee the two week
drilling program in the field
Byrock Copper Gold Project
- Field work completed on the “the Pipes” prospects which are prospective for Cu-porphyry deposits in a newly interpreted segment of the Macquarie Arc
- Final data analysis and target ranking to be completed in September
- NSW Government co-funding drilling grant decision expected by 30 September
- Technical review panel to decide on a potential November RC drill program
Theseus Copper Gold Project
- Application ELA6903 has been granted as EL9805 – 100% owned by Altitude Minerals
- Positive field visit to meet landowners in the area and discuss access agreements
- Half of the project is subject to a 6-month exclusive Option to purchase the tenements from Rimfire Pacific Mining, subject to DD and ministerial approval for transfer
- Further technical due diligence was undertaken, including a review of the historical core at the
NSW Core library, building out a 3D model, and historical data analysis - NSW Government co-funding geophysics and drilling grant decision by 30 September
- Technical merit decision to purchase Rimfire tenements to be determined
- Multiple site visits were recently completed in Nevada, with a focus on epithermal-style gold silver-antimony projects
- Technical due diligence is ongoing on multiple properties in the USA
- The Altitude team conducted a site visit to recently staked claims near Delta Junction,
Alaska, prospective for gold. Our team recovered historical core, which requires reboxing
before proper review and collected check samples for assay from historical trenching and
outcrops. Fortunately, we also obtained paper records of nearly all historical exploration that
were previously thought to be lost. The digitisation of paper records is ongoing. Once the
check assays are returned, core checked, and the historical review is completed, a technical
report will be released to the market, and decisions on next steps will be made. This will take
a few months to complete.
MORE INVESTOR UPDATES
Investor Presentation: Pipeline of Targets (Noosa Conference Nov 2025)
Altitude Minerals – A pipeline of targets

Drilling Commenced Cu-Au Porphyry Targets in the Macquarie Arc, NSW
Drilling has commenced to test the seven highest-ranked shallow “pipe-like”geophysical features analogous to North Parkes and Cadia Cu-Au porphyry deposits

Exploration Update: November 2025
An update on the exploration work and plans for Altitude’s projects for October & November

Altitude Minerals Awarded Critical Minerals Drilling Grant
$80,000 NSW Government drilling grant has been awarded under the Critical
Minerals and High-Tech Metals Exploration Program to drill the T55 Target at Byrock project in Macquarie Arc, NSW

Field Work Underway At the Firenze Silver & Gold Project, Nevada, USA
The Altitude Minerals’ team has immediately commenced field work to advance the Firenze Silver & Gold Project
to drill ready for early 2026

Quarterly Activities Report: September 2025
Catch up on all the latest Activities with this Quarterly Report