A detailed review was completed to re-rank all exploration targets across Gawler Craton tenements using geological information from drilling to date and newly acquired geophysical data.
Highlights and recommendations of the Project review
- Focus on the flagship Peake Project in the NE Gawler Craton, prospective for large- scale copper (IOCG) deposits
- A detailed project review has identified over 20 shallow potential IOCG targets less than 500m deep and a further six deeper targets at the Company’s Peake Project
- Drilling at the Billa Kalina Project and review of the North Titan Projects have
downgraded prospectivity and will be relinquished - The Gawler Craton is host to world-class IOCG deposits and includes Carrapateena
and the world-renowned BHP Olympic Dam Mine - Targeted infill geophysics (IP, gravity and AMT) surveys will inform the final target
ranking and refine drill collar locations - Extensive 6-month drilling program to commence in 2023
- A revised exploration strategy completed by the newly formed exploration team, using
a mineral systems approach and incorporates multiple big data sets, innovative peer- reviewed emerging techniques, and well-established conventional exploration methods
CORPORATE
Cash position of $8.2 million at quarter end 30 September 2022
The Gawler Craton is a world-class mining district in South Australia and is endowed with over 100 million tonnes of copper and 110 million ounces of gold. Copper Search’s Peake Project covers over 5,560 sq km giving the company a strong ground position in the district.
MORE INVESTOR UPDATES

Byrock Project Drilling Results
Assays have been received for the completed RC drilling.

Exploration Update: August 2026
An update on the exploration work and plans for Altitude’s projects

Altitude Expands W-Project Land Position
The new claims secure potentially prospective along-strike ground, interpreted to extend the structures hosting the W-Project quartz-calcite epithermal vein system
Quarterly Activities Report: June 2026
Catch up on all the latest Activities with this Quarterly Report

Exploration Update: July 2026
An update on the exploration work and plans for Altitude’s projects

Drilling Commenced At Byrock Copper Gold Project, Macquarie Arc – NSW
Drill permit issued and drilling rig contracted for 2,300m RC program to test three highest priority Pipe Targets